Entry/Exit Capacity Availability

... Show capacity situation for Entry/Exit point
Firm Entry capacity
5.2.2025technical cap. [GWh/d]Free technical capacity [GWh/d] Ready for auction [GWh/d]Contracted unbundled capacity [GWh/d] Contracted bundled capacity [GWh/d] Free unbundled capacity / STUIOLI*) [GWh/d] free longterm capacity overnomination
BP - Entry Point Kirevo / Zajecar 366.731 712 0.000 000 0.000 000 366.731 712 0.000 000 0.000 000N/AYES
*) Additional capacity released via CMP procedure.
Firm Exit capacity
5.2.2025technical cap. [GWh/d]Free technical capacity [GWh/d] Ready for auction [GWh/d]Contracted unbundled capacity [GWh/d] Contracted bundled capacity [GWh/d] Free unbundled capacity / STUIOLI*) [GWh/d] free longterm capacity overnomination
BP - Exit Kiskundorozsma 1200 245.765 592 0.000 000 0.000 000 245.765 592 0.000 000 0.000 000N/AYES
BP - Exit Point Serbia 120.966 144 0.000 000 0.000 000 120.966 144 0.000 000 0.000 000N/AYES
BP - Virtual Compress Station 3.000 000 0.000 000 0.000 000 4.000 000 0.000 000 0.000 000N/AYES
*) Additional capacity released via CMP procedure.
Interruptible Capacity - Entry
5.2.2025Available INT capacity [GWh/d] Contracted unbundled INT capacity [GWh/d]
BP - Entry Point Kirevo / Zajecar 25.798 296 0.000 000
Interruptible Capacity - Exit
5.2.2025Available INT capacity [GWh/d] Contracted unbundled INT capacity [GWh/d]
BP - Exit Kiskundorozsma 1200 22.133 592 0.000 000
BP - Exit Point Serbia 4.468 240 0.000 000
BP - Virtual Compress Station 2.196 488 0.000 000